What is Lnett up to?

2 strategic moves read from public sources, up to 1 Nov 2026.

Advancing Solborg transformer station Preparing new 132 kV line

Advancing Solborg transformer station

Lnett appears to be progressing the Solborg transformer station toward the implementation phase, while awaiting final regulatory approval before construction can begin.

Public records show that Lnett has submitted an updated detailed plan and forwarded hearing letters to landowners, and that NVE listed the plan as a hearing case with a deadline of 5 November 2026, indicating formal procedural advancement.

  1. Lnett asked questions about further processing for Solborg transformer station, indicating active clarification with authorities.

    einnsyn.no

  2. NVE requested Lnett to confirm that a hearing letter had been sent to landowners and other affected parties, showing regulatory follow‑up.

    einnsyn.no

  3. NVE listed the Solborg detailed plan as an active hearing case with a deadline of 5 November 2026, noting that approval is required before construction can start.

    nve.no

  4. Lnett reported forwarding the hearing letter to landowners and other affected parties, indicating the project is moving through formal hearing and clarification.

    einnsyn.no

  5. NVE confirmed receipt of an updated detailed plan for Solborg transformer station, showing the case is active with the energy authority.

    einnsyn.no

  6. Lnett submitted an "Updated detailed plan – Solborg transformer station," indicating the project is in a concrete planning phase.

    einnsyn.no

Preparing new 132 kV line

The company appears to be planning a new 132 kV transmission line between the Fagrafjell substation and Ålgård, together with a new transformer station at Ålgård. This infrastructure would expand the grid in the Rogaland region.

Public filings show that a concession application for the line and transformer station has been submitted to the regulator, and that the authorities have requested additional information, indicating the project is under active review.

  1. Lnett states there is a need for a new 132 kV power line between Fagrafjell and Ålgård and a new transformer station at Ålgård, and that the concession application has been sent to NVE for processing.

    l-nett.no

  2. The authorities asked for more information on Lnett's concession application, showing the application is under active treatment and may require further project development.

    einnsyn.no

  3. Lnett applied for a concession for the 132 kV power line Fagrafjell–Ålgårdslåtten, including the Ålgårdslåtten transformer station.

    einnsyn.no

Paldo wrote this page from the public sources linked above. What a company appears to intend is our reading and may be wrong. If something is out of date, tell us.

Company logos provided by Logo.dev.

See more companies

See it live

Want to see what Paldo can track in your market?