Preparing capacity lift at Lefdal
Lefdal Mine Datacenter appears to be gearing up for a substantial increase in power capacity and high‑performance computing capability. The plan includes expanding from its current output toward a larger, possibly 200 MW, footprint with dedicated liquid‑cooled HPC resources.
Public signals include a consent approval from the Labour Inspection Authority, a modest staff increase, and a presentation outlining an 80 MW‑to‑200 MW expansion path. Additionally, a major equity investor now manages the majority of the company’s equity, supporting the scaling effort.
-
The registered employee count rose from 55 to 59, a small staffing increase.
-
The Labour Inspection Authority approved Lefdal Mine Datacenter’s consent application, a concrete regulatory step typically linked to planned construction, installation or operational activity.
-
An October 2026 Lefdal presentation shows high density for HPC, around 60 employees and a stated expansion path from 80 MW to 200 MW, including 10 MW of direct liquid‑cooled HPC capacity.
-
3i describes Lefdal as an acquired data‑center platform and notes that 3i manages 90 percent of the equity in LMD, with new third‑party capital invested together with 3i Infrastructure, strengthening the picture of an institutional capital base supporting further capacity development.