Preparing data center in Arendal
Bulk Infrastructure appears to be moving forward with a large data‑center project at the Longum Nord site in Arendal. The plan includes securing substantial power capacity and formalizing a dedicated business unit for data‑infrastructure.
Public records show that the municipality approved the sale of the Longum Nord parcel to Bulk, that the company has applied for 150 MW of electricity for the site, that zoning changes were filed to permit data‑center use, and that a dedicated Bulk Data Centers Arendal registration exists. Media reports also note a purchase price of about 600 million kr.
-
Dagsavisen reports that Arendal approved the sale of the Longum Nord parcel to Bulk Infrastructure for a data‑center development.
-
TU reports that Bulk applied for 150 MW of power for the site outside Arendal, linking the request to the data‑center project.
-
Arendal municipality scheduled a site inspection related to the zoning amendment for Eyde Material Park, indicating the planning process is active.
-
Arendal municipality posted a zoning amendment for Eyde Material Park, Longum Nord, opening two zones for data‑center purposes.
-
Finansavisen notes that Bulk purchased a parcel for approximately 600 million kr.
-
The business register shows a dedicated Bulk Data Centers Arendal entity with an industry code for data‑infrastructure, processing and storage.