atNorth appears to be building a more industrialized and standardized execution platform for very large data‑center campuses across the Nordics. The effort includes expanding its talent pipeline and securing energy and grid connections for multiple sites.
Public signs include the development of the 300 MW SWE04 campus in Långsele with land purchase, approved plans and a 200 MW grid‑connection agreement; a heat‑recovery partnership with Calentix; construction permits for the Krageris project in Varde; topping out of the FIN02 expansion near Helsinki; and procurement manager roles advertised in Kista and Oslo.
Business Sweden reported that atNorth is developing the SWE04 campus at Hamre Industrial Park in Långsele as a planned 300 MW AI, HPC, cloud and enterprise site, with renewable energy, direct liquid cooling, heat‑recovery plans, a land purchase agreement, approved development plan, groundwork permit and a 200 MW grid‑connection agreement with E.ON.
Energy Loop reported that atNorth and Calentix signed a Project Development Agreement for SWE04 in Sollefteå, with Calentix handling financing and operations for a heat‑recovery project that could supply waste heat from the data centre to Långsele.
Varde Municipality has granted building permits for two of four planned greenhouse phases and the first of four data‑center halls at atNorth's Krageris project, with the wider plan covering 225,000 m² of data centres and 475,000 m² of greenhouses.
atNorth is hiring a Project Procurement Manager in Oslo to manage RFQ/RFP processes, bid evaluation and negotiations with general contractors and key suppliers, while supporting land development, demolition planning and site preparation.
atNorth is hiring a Project Procurement Manager in Kista to run RFQ/RFP processes, bid documentation, contract negotiations and site visits for construction packages, while also supporting pre‑construction work such as land development, demolition planning and site preparation for Nordic data‑center projects.
atNorth has topped out its FIN02 expansion outside Helsinki, with Skanska continuing as construction partner on the approximately €100 million project, scheduled for completion in Q3 2027.
atNorth appears to be shifting its first data center development in the Haugesund/Tysvær area from planning toward concrete project mobilization. The company is recruiting senior project and site‑development roles to manage construction delivery, permitting, stakeholder engagement and contractor negotiations.
Public signs supporting this reading include a recruitment notice for a Project Manager in Haugesund to lead end‑to‑end building delivery for a 120 MW first phase, a Site Development Manager role focused on local permits and public hearings, and a reported agreement for 120 MW of grid capacity with a partner.
Local reporting states that atNorth has entered an agreement with Fagne for 120 MW of grid capacity.
atNorth is seeking a Project Procurement Manager in Oslo responsible for RFQ/RFP processes for construction packages, tender documentation, contractor negotiations, site visits and pre-construction support, including land development, demolition planning and site preparation.
atNorth is seeking a Site Development Manager in Haugesund responsible for local stakeholder management, permits, approvals and public consultation for a data-center project.
atNorth is seeking a Project Manager in Haugesund for its Norway development team and its first data-center project in Haugesund. The role will manage end-to-end building delivery, schedule, critical path, risk, quality, procurement and contractor negotiations for a first phase of 120 MW.
atNorth appears to be moving the DEN02 data‑center and greenhouse development in Varde towards the start of construction, with a total‑contractor appointed and the first building phase slated for late 2026. The initiative involves multiple data‑center halls, greenhouse facilities, emergency power solutions and a substantial power supply agreement.
Public records show a series of local authorisations – including building permits for two of four planned greenhouse structures and the first data‑center hall, environmental clearance for emergency generators, and the selection of TSL as total‑contractor – indicating that the project is progressing through concrete regulatory and infrastructure steps.
Local media reports that Varde Kommune granted building permits for two of four planned greenhouses and the first of four data‑center halls in Krageris, with a 60 MW supply agreement for 2027‑2028 and dialogue about 500 MW to 2029.
Varde Kommune granted environmental approval for atNorth’s emergency generators for the Krageris data‑center, a concrete operational permit normally required before a larger data‑center can be realised.
Varde Kommune also issued a connection permit for the same DEN02 project, indicating that local infrastructure and technical clarifications are actively part of the implementation process.
Varde Kommune published a permit package related to excavation for atNorth’s data‑center and greenhouse project, showing the project is passing specific local authority gates.
Local industry coverage reports that Varde approved the planning basis for the 174‑hectare DEN02 project, and TSL was selected as total‑contractor for the project.
atNorth states that Varde council’s approval of the local plan makes it possible to start preparations for building DEN02, with the first construction phase expected in Q4 2026.
The company appears to be moving forward with supplier and construction mobilization for the SWE04 data‑center project in Långsele/Sollefteå.
Public indications include a Project Development Agreement with Calentix for heat‑recovery financing and operation, recruitment of a Construction Manager (MEP) and a Site Manager for large‑scale data‑center builds, and a series of municipal meetings that shared building plans and upcoming procurement details with local contractors and service providers.
Energy Loop reports that the company and Calentix have entered a Project Development Agreement for SWE04, with Calentix handling financing and operation of a heat‑recovery project delivering surplus heat to Långsele.
The company is seeking a Construction Manager MEP in Sollefteå for delivery of mechanical, electrical and plumbing systems on large data‑center projects, including contractor coordination, planning, commissioning and hand‑over to operations.
Sollefteå municipality notes that two business meetings were held about the company’s establishment in Långsele, where local firms received information on building plans and upcoming purchases ahead of construction start.
Sollefteå municipality invited local contractors, tradespeople and accommodation providers to a meeting with the company before construction start at Hamre Industrial Park, indicating that construction start is approaching.
The company is seeking a Site Manager in Sollefteå for large data‑center projects, responsible for site follow‑up from planning to completion, contractor coordination, progress meetings, procurement support, quality control and commissioning coordination.
Paldo wrote this page from the public sources linked above. What a company appears to intend is our reading and may be wrong. If something is out of date, tell us.